New Flagstone Walk & Steps (VA)
Back to Portfolio

Before
In VA, ES GroundsCare builds a new entrance lead walk and steps capped in flagstone.
The first step was to begin demolition of the old concrete walk and steps
with a compressor and jackhammer.

During
Next, the new walk is widened from 3 ft to 4 ft, and the new shape is framed.

Concrete is then poured, and in 24 hours the flagstone work begins.

After covering the main walkway, work begins on the new steps.

After
Day 3, block is used to build new steps, and then all the surfaces are covered in flagstone as well.